CR-2026-04-18: Rack Relocation — Risk Assessment
Risk Assessment
| Risk | Likelihood | Impact | Mitigation |
|---|---|---|---|
Drive failure from physical shock |
Low |
High |
Borg backup pre-move, XML dumps to workstation |
Loose cable post-move |
Medium |
Low |
Photo cables before disconnecting |
Power surge on startup |
Low |
High |
UPS with surge protection, staged power-on |
VMs fail to start |
Low |
Medium |
XML backups, manual virsh define |
Vault sealed after restart |
High |
Medium |
Expected — unseal keys in gopass |
Services start in wrong order |
Medium |
Medium |
Manual startup per this procedure, no autostart |