MSCHAPv2 Migration: Planning
Migration Waves
| Wave | Device Type | Count | Contact | Status |
|---|---|---|---|---|
1 |
Chromebooks |
1,754 |
Paul Tran (ptran@chla.usc.edu) |
Pending - Schedule meeting |
2 |
WYSE Thin Clients |
857 |
Andrew Rolle (arolle@chla.usc.edu) |
Pending - Schedule meeting |
3 |
Windows Domain |
270 |
Intune Team |
Pending |
4 |
macOS |
331 |
JAMF Team |
Pending |
5 |
iOS/iPhone |
1,760 |
Intune/JAMF |
Pending |
Timeline (Proposed)
| Phase | Duration |
|---|---|
Planning & Wave 1 Pilot |
4 weeks |
Wave 1 Rollout |
4 weeks |
Wave 2 Pilot + Rollout |
5 weeks |
Waves 3-5 (parallel) |
6 weeks |
Total |
~4 months |
Stakeholders
-
Paul Tran - Chromebook team
-
Andrew Rolle - WYSE team
-
Intune Team - Windows/iOS
-
JAMF Team - macOS/iOS
-
Sarah Clizer (CISO) - Executive sponsor