MSCHAPv2 Migration: Planning

Migration Waves

Wave Device Type Count Contact Status

1

Chromebooks

1,754

Paul Tran (ptran@chla.usc.edu)

Pending - Schedule meeting

2

WYSE Thin Clients

857

Andrew Rolle (arolle@chla.usc.edu)

Pending - Schedule meeting

3

Windows Domain

270

Intune Team

Pending

4

macOS

331

JAMF Team

Pending

5

iOS/iPhone

1,760

Intune/JAMF

Pending

Timeline (Proposed)

Phase Duration

Planning & Wave 1 Pilot

4 weeks

Wave 1 Rollout

4 weeks

Wave 2 Pilot + Rollout

5 weeks

Waves 3-5 (parallel)

6 weeks

Total

~4 months

Stakeholders

  • Paul Tran - Chromebook team

  • Andrew Rolle - WYSE team

  • Intune Team - Windows/iOS

  • JAMF Team - macOS/iOS

  • Sarah Clizer (CISO) - Executive sponsor